Alle Systeme funktionieren
Geplante Wartungen
Planned Network Upgrades on 08.01.2025

// English version: We would like to inform you that we will be carrying out scheduled maintenance on our network next Wednesday, 8 January 2025, from 03:00 to 09:00. As part of this maintenance, we will be replacing our corerouting and coreswitching stack with more powerful devices that will enable us to cope with growth. Due to the redundant network structure, there will be no noticeable outages as planned. However, as these cannot be completely ruled out, we are carrying out this maintenance at a rather uncritical time. We thank you for the trust you have placed in us and would like to take this opportunity to wish you a Happy New Year!

// German version: Wir möchten Sie informieren, dass wir am kommenden Mittwoch, den 08.01.2025, ab 03:00 Uhr bis 09:00 Uhr planmäßige Wartungen an unserem Netzwerk durchführen werden. Wir werden im Rahmen dieser Wartung unseren Corerouting- bzw. Coreswitching-Stack durch leistungsfähigere Geräte ersetzen, die uns ermöglichen, dem Wachstum gerecht zu werden. Durch den redundanten Netzaufbau wird es planmäßig nicht zu merkbaren Ausfällen kommen. Da diese jedoch nicht vollständig auszuschließen sind, führen wir diese Wartung zu einer eher unkritischen Zeit durch. Wir danken für das in uns gesetzte Vertrauen und wünschen an dieser Stelle ebenfalls ein frohes neues Jahr!

Vergangene Vorfälle

Sonntag 19th Mai 2024

Es liegen keine Vorfälle vor

Samstag 18th Mai 2024

Es liegen keine Vorfälle vor

Freitag 17th Mai 2024

Es liegen keine Vorfälle vor

Donnerstag 16th Mai 2024

Es liegen keine Vorfälle vor

Mittwoch 15th Mai 2024

Es liegen keine Vorfälle vor

Dienstag 14th Mai 2024

Fiber-Connection to FRA Frankfurt Fiber Outage due to power outage in Interxion FRA2 datacenter

At 12:02 the fiber line to Frankfurt failed, the traffic that is processed via Frankfurt was therefore automatically rerouted after a short interruption.

The reason for the outage is a power failure in the Interxion/Digital Realty FRA2 data center in Frankfurt. Other carriers are also affected by this, see for example the following status message: https://status.core-backbone.com/index.php?id=5081

Traffic is currently being routed transparently via Amsterdam and will be automatically rerouted as soon as everything is stable again.

  • The power supply in the Interxion/Digital Realty FRA2 data center and thus also the connection to Frankfurt has been restored since around 15:00. We waited until around 15:50 and monitored the situation. Since then, we have been routing traffic via the usual paths again.